State to ‘Off Ramp’ Key Bridge Contractor as Work Continues

 

 A hammer attached to a large crane drives a pile into the Patapsco riverbed, which will form part of the foundation of the new Key Bridge, on March 26, 2026, the two-year anniversary of the bridge collapse. (File photo by Christine Condon/ Maryland Matters)

 

State transportation officials vowed Tuesday to keep reconstruction of the Francis Scott Key Bridge on track, even as they part ways with the current contractor and begin the search for a new one.

State officials said Tuesday that the decision to part ways with Kiewit Infrastructure as the project enters phase two, came down to a disagreement on price for completing the project.

“We’ve been very pleased with the quality of the work and the timeliness of the work, and Kiewit will continue to do that work until it’s completed,” said Transportation Secretary Kathryn Thomson.

Under the terms of the initial contract, Kiewit began the design and planning of the new bridge. The contract required the state to negotiate first with Kiewit on an option on phase two construction.

Those negotiations continued over the last three weeks but bogged down on the issue of price.

Thomson said state officials worked with Kiewit to “better understand their bid and what we believe is a reasonable cost for the bridge.”

Maryland Transportation Secretary Kathryn Thomson said work on rebuilding the Francis Scott Key Bridge will continue as the state looks for a new contractor for phase two of the project. (File photo Bryan P. Sears/Maryland Matters)

The cost of that replacement is currently estimated at $4.3 billion to $5.2 billion. It is not expected to open until the end of 2030 — about two years later than originally projected.

“We ultimately decided that their bid was unacceptably high,” Thomson said. “We were not able to resolve the differences, although the discussions helped us better understand some of the source of the differences.”

Because of the impasse, Thomson said the state will “off ramp” Kiewit from the project.

Thomson declined to elaborate on the value of Kiewit’s bid, citing confidentiality restrictions.

The Nebraska-based firm joined the project in 2024. It will continue to work on the project until the end of the year. All told, the company will be paid about $700 million for its part in the project, according to transportation officials.

Thomson said the project will continue without interruption.

“We will go out to the market to seek competitive bids for phase two and expect to have contractors on board to ensure that there is no work stoppage and that we see continual progress to reconstruct the Key Bridge in the coming months,” she said.

Reconstruction started two years ago after the collapse of the Key Bridge in the early morning hours of March 26, 2024. The container ship Dali was leaving the Port of Baltimore that morning when it lost power. The fully loaded 985-foot ship went dark, drifted and eventually struck one of the piers of the bridge.

Within seconds, much of the span collapsed into the Patapsco River. Six members of road crew who were working on the bridge deck that morning died.

The collapse closed the Port of Baltimore for weeks. The ship was trapped under the fallen bridge decking. State, federal and private crews pulled 50,000 tons of steel and concrete from the shipping channel to reopen it to port traffic.

The National Transportation Safety Board, in a November report, said the collapse was the result of a power outage linked to a loose wire. But the agency also cited what it called “woefully inadequate” infrastructure protecting the Key Bridge.

Currently, the project includes about 30 of the nearly 1,000 pilings that will be required to build the new bridge. James Harkness, chief engineer for the Maryland Transportation Authority, said Kiewit continues to make progress on the project.

“They’re out there working two locations for driving those piles. Similarly, they’re working two locations on the construction trestle or the temporary work platform,” Harkness said. “So, they’re working on both sides, north and south there as well. So making good progress on all those activities.”

Then-President Joseph Biden (D) at the time of the bridge collapse promised full federal reimbursement for the project. The state, however, is responsible for forward-funding much of the work and seeking reimbursement.

At times, federal officials under President Donald Trump have raised questions about the security of that funding. The biggest concern is the potential for escalating costs.

“Maryland and the US Department of Transportation are aligned that we all have an obligation to deliver this bridge in a cost effective, timely and responsible way that meets the highest safety standards. There’s no daylight between us on that,” Thomson said.

“Yes, it is true that USDOT would like to bring this cost in as low as possible. That is also true for us too, but we will be guided by responsible project management, keeping tight control over risks,” she said. “But they … have not laid down a marker, and by law, they’re legally obligated to cover 100% of the costs.”

— This story may be updated.


Bryan P. Sears, Maryland Matters
April 28, 2026

Maryland Matters is part of States Newsroom, a nonprofit news network supported by grants and a coalition of donors as a 501c(3) public charity. Maryland Matters maintains editorial independence. Contact Editor Steve Crane for questions: editor@marylandmatters.org.

AI Disclosure: The Spy and its writers may use artificial intelligence tools to support accuracy and clarity in our reporting.

2 Responses

  1. MDOT has made a serious mistake in its termination with Kiewit. They are one of the best in building bridges worldwide. I had the opportunity to be an inspector on one of their projects in Connecticut. They are a first-class outfit. There are very few contractors that can build and be bonded for a project of this magnitude. The longer this Governor waits to find a general contractor, the higher the price will be. Prices are rising every day. Just look at the prices of gas and groceries.

  2. And while we’re at it, the F.S. Key Bridge was accidentally demolished well over a year ago. I am opposed to having its replacement — an entirely new structure — named for a slaveholder, which Key was. I suggest instead naming the brand-new bridge for either of two genuine American patriots and freedom fighters, Harriet Tubman (Dorchester County) or Frederick Douglass (Talbot County).
    Or, both!

Care to Comment on the Article?

We encourage readers to offer their point of view on this article by submitting the following form. Editing is sometimes necessary and is done at the discretion of the editorial staff. Your email address will not be published. Required fields are marked *. Please read our Guidelines for Public Comments.

  • 300x500 Talbot Spy Seaglass
  • unnamed
  • spy envision ad 2025 FINAL HIRES orange
  • Talbot Spy Ad
  • 0 1
  • Grassymeade Tech 3 copy
  • Talbot Spy Strategic Planning Final 600x1000
  • CWS AdsDataAxle2025
  • Bookplate Feb 2026 copy
  • Brampton Grape Expectations July 2026 ver 2 copy

Subscribe to the Spy
Receive daily intelligence reports right to your inbox

  • Pediatrics Chestertown Ad Fall (300x500) MECH
  • SRM 3231 General Ad SEP'25 (300x500)
CHESTERTOWN SPY
spy envision ad 2025 FINAL HIRES orange
massoni castelli DR Spy Artboard 1
Brampton Grape Expectations July 2026 ver 2 copy
Spy Downriggign Ad 2026
Camp26 300x500 respite
Talbot Spy Strategic Planning Final 600x1000
Chester River Chorale 2jpg
0 1
Grassymeade Tech 3 copy
CWS AdsDataAxle2025
Chester River Chorale 1
unnamed
300x500 Talbot Spy Seaglass